Scope Baseline

  1. The Scope Baseline consists of the approved version of the Project Scope Statement, the WBS, and the WBS Dictionary. We have previously discussed the 3 terms. 
  2. From an exam perspective, you need to remember that it is the finalized and approved version of the project scope statement, WBS, and WBS Dictionary. 
  3. Also,
    1. The Project Scope Statement is a detailed document
    2. The WBS is a visual representation
    3. The WBS Dictionary can be used to manage the actual work since it has all the details